Success Story | 72 Units | 12 Buildings | Factoria, Bellevue, WA
Challenge:
Broken condo conversion with $1M budget bust, demolition started in all 12 buildings, multiple liens, no permit application, and 87% vacancy.
Strategies:
Fully defined scope of work and rebid. Directed design solutions appropriate for a reversion to apartments and secured appropriate permits. Negotiated lien releases. Communicated strategy and progress to multiple lenders. Expedited completion to facilitate lease-up. Created and implemented a marketing campaign to generate significant traffic and qualified prospects.
Results:
- Increased NOI by 90% over pre-conversion operating numbers.
- Construction completed on budget.
- Unit inventory delivered predictably and ahead of leasing velocity.
- Siding scope completed under supervision of envelope consultant to facilitate a later conversion by a future owner.